Not all planning applications are the same. Picking the correct type of application saves you time and avoids rejection.
Popular searches:
Which planning application do I need to submit?
Whether you’re planning an extension, a loft conversion or just knocking down a wall, it’s important to know what kind of approval your work needs.
Applications at a glance
| Application type | Typical use | Decision timeframe | Notes |
|---|---|---|---|
| Householder planning | Single home extensions and alterations | 8 weeks | Most common for home improvements |
| Full planning | Changes and extensions to flats, new builds, flat conversions | 8 weeks | Detailed design plans needed |
| Prior approval | Permitted Development works that require approval from the Council prior to starting | 6-8 weeks | For larger home extension projects or change of use |
| Lawful Development Certificate | Evidence that planning permission isn't needed | 8 weeks | Optional but recommended |
| Listed building consent | For interior or exterior works to a listed building | 8 weeks | It is a criminal offence to start works that require listed building consent without the consents in place. |
Householder planning application
Used for: Most extensions and improvements to individual houses.
Examples: Conservatories, porches, loft conversions, garages, boundary walls.
Typical decision time: Around 8 weeks.
Download our Validation Checklist to see exactly what’s needed for this application >>
Full planning permission
! If you live in a flat or maisonette, you will need Full Planning Permission for ANY change you want to make in your property.
Used for: This is the most thorough type of application and is typically needed when building something completely new, or making major changes to an existing property
Examples: Most extensions and improvements to individual flats. Building a new home or converting a house into flats.
Typical decision time: Around 8 weeks.
Download our Validation Checklist to see exactly what’s needed for this application >>
Permitted development with prior approval
Used for: Some projects that fall under permitted development but still require the council’s confirmation on specific impacts (like size or neighbour amenity).
Examples: Larger home extensions or changes of use (like office to residential).
Typical decision time: Around 6-8 weeks.
Download our Validation Checklist to see exactly what’s needed for this application >>
Lawful Development Certificate
Used for: This is optional but strongly recommended, if you are carry out work under Permitted Development. It provides formal proof that your work did not need planning permission - useful if you sell your home or need to show evidence later.
Examples: single storey extensions, loft conversions, outbuildings carried out under Permitted Development.
Typical decision time: Around 8 weeks.
Listed building consent
Use: Listed building consent will nearly always be required for works to a listed building.
Examples: This includes any works to the interior of a listed building and to structures within its curtilage.
Typical decision time: 8 weeks
Still unsure?
If you are unsure about which type of application to make speak to us as soon as possible for more information on the different types of planning application, and special considerations. The council offers a pre-application planning advice service to help you get it right the first time.
Once you’ve chosen the right application, you may need drawings, a site location plan, and a few key documents.
You can prepare these yourself or ask an architect or planning consultant for help.
Don't forget Building Control
Even if you don’t need planning permission, if you are making changes to the inside of your home you may still need to get Building Control approval. These ensure your home is safe, energy-efficient, and structurally sound.